Inhouse production lead time impact on Sales deliv拜托各位了 3Q
Hi, We have a make to stock business scenario with Planning strategy 40 in which Sales order consume forecast.. we have maintained in house production time as 7days in Material master.Because of this in house production lead time the system always pushes delivery schedule line in sales order for another 7days even the product is available in the stock.If any one have idea how to fix this issue ? ThanksASBN

提问时间:2021-03-17

答案
My guess is that in strategy-40,sales order will consider stock only if it first gets a PIR to consume.If there are no PIRs to consume,then it assumes that stocks are allotted to other sales orders,so the earliest new stocks can come is after lead time days.Just create a PIR (within consumption period of that sales order) and then try creating sales order.In strategy-40,stocks cannot be more than sum of sales orders and PIRs.查看原帖>>
举一反三
我想写一篇关于奥巴马的演讲的文章,写哪一篇好呢?为什么好
奥巴马演讲不用看稿子.为什么中国领导演讲要看?
想找英语初三上学期的首字母填空练习……
英语翻译
1,人们染上烟瘾,最终因吸烟使自己丧命.
版权所有 CopyRight © 2012-2019 超级试练试题库 All Rights Reserved.